Cassava starch project

Indonesia projects

Zhengzhou Jinghua Industry Co.,Ltd Zhengzhou Jinghua Industry Co.,Ltd

These two cassava starch projects were established in 2010 and capacity are both 12T/H.

The first project was signed in Aug, 29, 2009, between ZHENGZHOU JINGHUA INDUSTRY CO., LTD and PT.DUNGO REKSA, an Indonesia company. Most of the installation work was complete in April, 2010 except for drying pipes and peeler centrifuge. This project was ceased till now because of capital turnover problem of local investor.

The second project was signed in Nov, 11, 2009, between ZHENGZHOU JINGHUA INDUSTRY CO., LTD and PT.HUTAHAEAN, an Indonesia company. This plant has been successfully running after the opening ceremony in Dec, 4, 2010.